SAP Factory Calendar

' src=

IMG -> SAP NetWeaver -> General Settings -> Maintain Calendar

Steps to Define a Factory Calendar

There are three steps when defining the factory calendar:

  • Public Holidays

Holiday Calendar

  • Factory Calendar

Public Holiday

Public holidays are the statutory holidays in the calendar. These days can vary depending on the country and region. Most of the common holidays are pre-defined in SAP and we can use those. If there are any additional holidays, we can define them by going into the public holiday definition. When defining a public holiday, there are several options available.

  • Fixed day from the date
  • Distance to easter
  • Easter Sunday
  • Floating public holiday

The fixed date is used to define holidays that are fixed on a particular date, e.g., Christmas day. When defining a fixed holiday, we need to only give the month and the date within the month. When this holiday is assigned to a calendar, the fixed holiday will remain unchanged throughout the calendar validity period.

If a public holiday falls on a fixed weekday from a particular date, we can use the second option “ fixed-day from date ”. If a public holiday has a fixed distance to Easter Sunday, we can use the “ distance to Easter ” option. If the holiday is Easter Sunday, then we can use the “ Easter Sunday ” option. If there is no specific rule for the holiday, we can use the last option which is “ floating public holiday ”. For floating holidays, we need to define the month and date for every year because the date will change each year.

There are several other inputs that we can give during holiday definition.

  • Sort criteria
  • Public holiday class
  • Short holiday name
  • Long holiday name

After defining the public holidays, we can define a holiday calendar. This is kind of a grouping for the holidays. When defining the holiday calendar, the below inputs must be entered:

  • Calendar ID – Unique ID which is used to identify the holiday calendar.
  • Calendar name – Give a name for the calendar.
  • Validity period – A validity period must be given for each holiday calendar.
  • Assignment of public holidays – Assign the public holidays that we defined in the previous step.

When the holiday calendar is already assigned to a factory calendar, the “ used in factory calendar ” indicator will be set against the holiday calendar.

The final step of the calendar definition process is to create the SAP factory calendar. Below are the inputs that need to be given:

  • Factory calendar ID – Unique ID used to identify the factory calendar.
  • Factory calendar name – A name can be given for the calendar.
  • Validity period – Validity period must be defined.
  • Holiday calendar ID – Enter the holiday calendar ID that is relevant to the factory calendar. This will assign the public holidays in the holiday calendar to the factory calendar.
  • Workdays – Define the days which are considered as workdays in the week.
  • Special rules – If there are any additional holidays that we need to assign only for this factory calendar, we can set those up as special rules.

Once the factory calendar is defined, it can be assigned to the plant code. This marks the completion of factory calendar creation in SAP. —

Did you like this tutorial? Have any questions or comments? We would love to hear your feedback in the comments section below. It’d be a big help for us, and hopefully, it’s something we can address for you in the improvement of our free SAP PP tutorials.

Navigation Links

Go to the next lesson: SAP BOM Tables

Go to the previous lesson: SAP Production Version

Go to overview of the course: SAP PP Training

Leave a Reply Cancel reply

Do you have a question and want it to be answered ASAP? Post it on our FORUM here --> SAP FORUM !

Your email address will not be published. Required fields are marked *

Save my name, email, and website in this browser for the next time I comment.

Online Tutorials & Training Materials | STechies.com

  • What is SAP PM?
  • SAP PM Training Tutorials for Beginners
  • SAP PM Transaction Codes
  • BAPI's for Plant Maintenance
  • Class and Characteristics in SAP PM
  • SAP PM Order Types
  • Catalog Profile in SAP PM
  • SAP PM Certification Cost in India
  • SAP PM Interview Questions and Answers

Assign Factory Calendar to Plant in SAP

Updated May 03, 2022

This SAP PM tutorial explains to the SAP users the step-by-step procedure to assign a Factory Calendar to a Plant in the SAP ERP system with proper screenshots.

Once the user has created a new Factory Calendar in the SAP system, the user next needs to assign the newly created factory calendar to a plant in SAP. This assignment is required so that every plant can schedule its task according to the calendar.

Read Here: Create Factory Calendar in SAP

How to Assign Factory Calendar to Plant in SAP?

Please follow the steps below to assign a factory calendar to a plant in SAP:

Execute the t-code OX10 in the SAP Command Field as shown in the image below:

OX10

Next, click the Position button,enter the plant key TKKL (or any plant that you want to assign the factory calendar), and press the Enter button, so that the plant code displays on top of the SAP screen.

Position button

Now select the plant key and click on the Detail icon (magnifying glass) present at the status bar to display the details.

Details

Now on Change View "Plant": Details screen scroll down and enter the factory holiday calendar key in the field Factory Calendar as shown in the image below.

Factory Calendar

Once the assignment of the calendar is done, click the Save icon to save the new configuration details.

Save

A message Data was saved will be displayed on your screen implying that the new configuration has been saved in your SAP system.

Data was saved

You have successfully assigned the factory calendar to a plant TKKL in the SAP system

IMAGES

  1. SAP PM

    assignment of factory calendar in sap

  2. SAP PM

    assignment of factory calendar in sap

  3. SAP PM

    assignment of factory calendar in sap

  4. SAP PM

    assignment of factory calendar in sap

  5. Factory Calendar in SAP?

    assignment of factory calendar in sap

  6. SAP PM

    assignment of factory calendar in sap

VIDEO

  1. CPSC 3148-01: Calendar Tutorial (Pt. 2 of Assignment 1)

  2. sap withholding tax configuration

  3. SAP Assignment 2 Walk Through

  4. Hitachi Hi-Rel Make UPS

  5. Introduction to Spark School Software

  6. The Time Factory Calendar Company

COMMENTS

  1. SAP PM

    After you define/ create factory calendar in SAP, you need to assign to plant. Perform the following steps for assignment of calendar to plant. Step 1 : - Execute t-code "OX10" in command field. Step 2 : - Click on position button and enter plant key "TLBL" and press enter, so that plant code displays on top of the SAP screen.

  2. SAP Factory Calendar Tutorial

    Validity period - A validity period must be given for each holiday calendar. Assignment of public holidays - Assign the public holidays that we defined in the previous step. When the holiday calendar is already assigned to a factory calendar, the "used in factory calendar" indicator will be set against the holiday calendar. SAP Factory ...

  3. PDF SAP PM

    How to create factory calendar in SAP Factory calendar consists the number of working days with weekend and holidays. With the help of factory calendar, the planning in an organization can be done accordingly, as the SAP system will advise if the work ... assignment of calendar to plant. Step 1 : - Execute t-code "OX10" in command field ...

  4. Create and Assign Factory Calendar

    To create and assign a factory calendar in SAP, you can follow these steps:Creation of a factory calendar:a. Go to transaction code SCAL.b. Click on the "Fac...

  5. What is Factory Calendar in SAP

    This video helps to understand the concepts of the Factory Calendar and the setup procedure in SAP.Supporting OSS notes: 501670 - Public Holiday Calendar Cre...

  6. Factory Calendar

    On this page. Creating a Runtime to Access Calendar-Related Information. Reading Factory Calendar-Related Information. Reading Holiday Calendar-Related Information. Reading Holiday-Related Information. Mapping between SCAL-relevant IDs and FHC-relevant IDs. Reading Additional Factory Calendar-Related Information.

  7. Factory Calendar

    Factory calendars. A factory calendar is based on a country-specific holiday calendar and defines which days are working days, for example, Monday to Friday, and location-specific rules. Read on to learn about the set of data we deliver for these categories. Note. Class CL_SCAL_API is still available, but deprecated.

  8. SAP Factory Calendar Customizing

    SAP Factory Calendar Customizing0:00 What is Factory Calendar?4:11 Customize Factory Calendar23:20 Assign Factory Calendar to Org. Units.

  9. Factory Calendar in SAP?

    Enter t-code SCAL in the SAP command field and press Enter to execute it. Next to the SAP Calendar: Main Menu screen, select the option Factory Calendar and click on change icon. Now on the Change Factory Calendar: Overview screen, click on the Create icon. Next on the Change Factory Calendar Details screen, enter the following details for the ...

  10. Factory Calendar Settings and Use

    This setting defines that the factory calendar doesn't apply for the planning of a specific task, meaning that a task can also start on non-workdays. This way, tasks of the type Job can, for example, run during the weekend so that they are finished by the time you return to work after the weekend. Example. Example 3: Ignore Factory Calendar.

  11. How to Assign Factory Calendar to Plant in SAP?

    Execute the t-code OX10 in the SAP Command Field as shown in the image below: Next, click the Position button,enter the plant key TKKL (or any plant that you want to assign the factory calendar), and press the Enter button, so that the plant code displays on top of the SAP screen. Now select the plant key and click on the Detail icon ...

  12. Factory Calendar

    Maintain Holiday Calendars. Maintain Factory Calendars. i18N Services. Identity and Access Management. Message Monitoring. Output Management. Read Access Logging. Security. System Management.

  13. Cup Noodles wants to rethink the way you eat ramen with new s'mores

    Ramen isn't the first food to come to mind when you think of sweet treats. Cup Noodles is trying to change that — with a new s'mores-flavored instant ramen.

  14. Using Factory Calendars

    Factory calendars influence the generation of order and delivery schedules because they contain information about the days on which sources and recipients are open and closed. They also include information about public holidays, which are usually defined as non-working days.